Bulk Costing Menu Reference
The Bulk Costing & Analysis window provides the following commands and features on both the right-click context menu and the Edit menu. (Some of these features are also available as fields in Bulk Costing tabular user interface ):
Menu Command
Description
Copy Entire Table
Copy
Paste
(Edit menu only) Copy applies to the currently selected row(s). Copy Entire Table is useful for capturing all contents of the window for pasting into a spreadsheet or other document. Paste copies clipboard data into the table. See Editing bulk costing inputs above for details.
Create From This Row
Create a new row in the Bulk Costing & Analysis UI using an existing row as a starting point. See To edit, add, and refresh components from a bulk cost group above for details.
Edit Production Info
Edit Administrative Info
Edit Quoted Cost
Edit Process Routing
Edit Cost Overrides Summary
Edit Process Setup Options
For Production Info, Administrative Info, and Quoted Cost, see the description at Using the Cost Object Info window.
For Process Routing, see Selecting a process routing.
For Process Setup Options, see Editing process setup options.
Make Official
Undo Make Official
Specify whether or not the selected scenario is to be made the scenario that by default gets rolled into its parent assembly or roll-up. See the description for the Scenario menu in the main UI at Working with scenarios.
Make Active (Scenario)
Make Inactive (Scenario)
Specify whether or not the selected scenario is automatically updated with CAD changes. See the description for the Scenario menu in the main UI at Working with scenarios.
Extract GCDs
Do Not Extract GCDs
Controls whether or not aPriori should re-extract the latest geometry of the CAD model. If you are sure that the geometry of a component’s CAD file has not changed since the last time the part was costed and saved in the aPriori database, then you can choose to not extract GCDs. aPriori will simply use the previously-saved set of GCDs without re-analyzing the CAD model, reducing the total amount of time required for aPriori to cost the component.
Deep Cost
Undo Deep Cost
Set whether or not deep costing is enabled. See Scenario support fields for more details.
Edit Processing Input Rule...
Specify how aPriori should handle existing scenarios. See the description at Scenario support fields for more details.
Ignore
Undo Ignore
If a component scenario is set to "ignore", the component scenario will not be costed even if it is a sub-component of a deep costing assembly. See the section "A note about Ignore, Hide, and their effect on costing" in the aPriori Cost Model Guide for more details.
Ignore Excel Inputs
Undo Ignore Excel Inputs
Control whether fields in the Bulk Costing & Analysis UI are updated from the Excel input file or can be edited locally. See To edit, add, and refresh components from a bulk cost group for more details.
Select Image File
(Context menu only) Specify the full path of a 2D image file to associate with a CAD-less (virtual) part or assembly. See Associating an image without a CAD file for more details.