Turret Press, Laser Punch, Plasma Punch
aPriori uses the formulas below to determine costs associated with this process.
Accounting Calculations
Labor Time = Cycle Time * Machine Labor Time Standard
Labor time is the product of the following
Cycle time (see Cycle Time Calculation)
Machine labor time standard (specified as a machine property). This value reflects the amount of time spent by machine operators in between machine cycles, including time performing maintenance and cleaning tasks as well as time pausing between tasks. The amount is expressed as a cycle time multiplier.
Labor Cost = (Labor Time / 3600) * Machine Labor Rate
Labor cost is a function of the following:
Labor time (see formula above)
Machine labor rate (specified as a machine property)
Amortized Batch Setup = Machine Setup Time * Machine Labor Rate / Batch Size
Amortized batch setup is a function of the following:
Machine setup time (specified as a machine property)
Machine labor rate (specified as a machine property)
Batch size (specified in the Production Info dialog)
Period Overhead = 0
Period overhead is always 0.
Cycle Time Calculation
Cycle Time = Punch Time + Nibble Time + Tool Change Time +
(Machine Labor Handling Time / Number of Parts Per Sheet)
Cycle time depends on the following:
Punch time
Nibble time
Tool change time (increases with increased variability in feature dimensions)
Machine labor handling time (obtained from lookup by part mass in smTurretPressHandling)
Number of parts per sheet (calculated based on part geometry, nesting type, and sheet dimensions)
Expendable Tooling
Expendable Tooling Cost = (Special Hole Tool Avg Cost * Small Special Tools) +
(Countersink Tool Avg Cost * Countersink Tools) +
(Form Tool Avg Cost * Form Tools) +
(Perforate Tool Avg Cost * Perforation Tools)
Expendable tooling cost depends on the number and cost of the various types of tools.