Cut-to-Length, Shear
aPriori uses the formulas below to determine costs associated with these processes.
Accounting Calculations
Labor Time = Cycle Time * Machine Labor Time Standard
Labor time is the product of the following
Cycle time (see Cycle Time Calculation)
Machine labor time standard (specified as a machine property). This value reflects the amount of time spent by machine operators in between machine cycles, including time performing maintenance and cleaning tasks as well as time pausing between tasks. The amount is expressed as a cycle time multiplier.
Labor Cost = (Labor Time / 3600) * Machine Labor Rate
Labor cost is a function of the following:
Labor time (see formula above)
Machine labor rate (specified as a machine property)
Amortized Batch Setup = Machine Setup Time * Machine Labor Rate
Amortized batch setup is a function of the following:
Machine setup time (specified as a machine property)
Machine labor rate (specified as a machine property)
Cycle Time Calculation
Cycle Time = (1 / Machine Cut Speed) + Handling Time
Cycle time depends on the following:
Machine cut speed
Handling time (obtained from the lookup table smShearHandling, increases with part mass, which increases with material density)