Applying Mold Release Operation
Applying mold release is a labor-dependent task (see Labor-dependent and Labor-independent Tasks).
Cycle Time = Apply Mold Release Time / Number of Operators
Cycle time depends on the following:
Apply mold release time: this is the time it takes one operator to apply one coat of mold release to the tool. See formula.
Number of operators: by default, this is specified by the machine property Number of Operators. Users can override the default with the setup option Number of Operators.
Apply Mold Release Time = Tool Surface Area / Apply Mold Release Rate
This is the time it takes one operator to apply one coat of mold release to the tool. It depends on the following:
Tool surface area: this is estimated based on the part dimensions and a perimeter allowance. See Tool Length, Width, and Area.
Apply mold release rate: this the application rate for one operator in area per unit time. It is specified by the cost model variable applyMoldReleaseRate (26,000mm2/sec in starting point VPE).
Additional Direct Costs =
Mold Release Cost Per Area * Tool Surface Area
This is the cost for the mold release material consumed in one coating of the tool. It is the product of the following:
Mold release cost per area (see formula)
Tool surface area: this is estimated based on the part dimensions and a perimeter allowance. See formula.
Mold Release Cost Per Area =
Mold Release Cost Per Volume /
Mold Release Coverage Rate Per Volume
Mold release cost per area depends on the following:
Mold release cost per volume: this is the value of the Cost Per Volume field for the tool shop variable named by Mold Release Agent.
Mold release coverage rate per volume: this is the area of mold covered by a given volume of release agent, in area per unit volume. It is looked up by Mold Release Agent in the too lshop Tool Materials table.