Forging costing details
The Forging process group uses the following costing rules:
The aPriori Baseline VPEs assume that only a single part is forged at one time. This affects part cycle times and costs, as well as tooling costs.
Tooling costs are computed for Hammer, Piercing Press, and Trim Press processes.
By default, for each forging process, aPriori selects lowest-cost machine with the capability or capacity for the part(s) being manufactured. For example, it will select the lowest cost Hammer with sufficient impact energy to forge the part).
If machining processes are included as secondary processes on forged components, then the machining costs are computed via the Machining cost model and combined with the Forging process costs to produce a total manufacturing process cost.