Piece Cost
Piece Cost = Material Cost + Labor Cost +
Direct Overhead Cost + Logistics Cost + Setup Cost + Other Direct Costs
Piece cost is defined in the Site cost model global taxonomy module. Piece cost is the sum of the following per part costs:
Material cost (result of aggregating material costs from the current node’s children)
Labor cost (result of aggregating labor costs from the current node’s children)
Direct overhead cost: see Overhead Costs per Part
Logistics cost (result of aggregating logistics costs from the current node’s children)
Setup cost: also known as “amortized batch setup”, this is the result of aggregating setup costs from the current node’s children.
Other direct costs (see Other Direct Costs)