Viewing options
The View menu gives you two options – Show Routings with Incomplete Cost and Show Uncosted Processes within Visible Routings. Using these options, you can create different views of the Operation Sequence Selection window:
If both options are unchecked, only the sequences that have been costed without warnings are displayed.
If the Show Routings with Incomplete Cost option is checked, sequences that costed with warnings and also available sequences that were not costed are displayed.
If the Show Uncosted Processes within Visible Routings option is checked, all uncosted nodes within the sequence are displayed. A node could be uncosted if the operation it is representing is not required for the GCD or has been manually excluded from the sequence.