Viewing options
The View menu gives you two options – Show Routings with Incomplete Cost and Show Uncosted Processes within Visible Routings. Using these options, you can create different views of the Operation Sequence Selection window:
• If both options are unchecked, only the sequences that have been costed without warnings are displayed.
• If the Show Routings with Incomplete Cost option is checked, sequences that costed with warnings and also available sequences that were not costed are displayed.
• If the Show Uncosted Processes within Visible Routings option is checked, all uncosted nodes within the sequence are displayed. A node could be uncosted if the operation it is representing is not required for the GCD or has been manually excluded from the sequence.